By Shakuntala Makhijani , Guest Columnist
Last month, electricity regulator, the Office of Utilities Regulation (OUR), released recommendations for Jamaica‘s anticipated electricity wheeling programme.
Electricity wheeling has been proposed in Jamaica as a way to promote distributed power generation, especially from renewable-energy sources.
Under the proposed wheeling programme, a company or individual could generate electricity in one part of the country and pay the grid operator – the Jamaica Public Service Company (JPS) – a fee to transport that power to another location where it will be used.
Because JPS currently has a monopoly on electricity distribution, a company would only be able to send electricity over the grid to be consumed at a location that it also owns. For example, a sugar company that generates electricity at a sugar refinery using bagasse can send excess power to its offices in Kingston to avoid paying high electricity bills there, but cannot sell electricity to another entity.
Several of Jamaica’s large energy consumers are considering participating in the forthcoming wheeling programme to support investments in renewable energy.
Hotel chain Sandals, the Caribbean’s largest poultry producer Jamaica Broilers, and the National Water Commission, the largest single electricity consumer in the country, all have plans to wheel power.
A National Irrigation Commission project using wind energy to power irrigation pumps also wants to participate in the programme.
Only for firm generation capacity
At a recent public consultation, however, OUR officials confirmed that the electricity wheeling programme will be intended only for firm generation capacity – meaning it will exclude variable renewable-energy sources such as solar and wind.
Electricity wheeling provides an opportunity to promote distributed renewable generation, especially at the large commercial or industrial scale (more than 100 kilowatts to several megawatts).
For this reason, Worldwatch has submitted a public comment to OUR recommending, based on our research in renewable energy transition in Jamaica, that the regulator reconsider its exclusion of variable capacity and open the electricity wheeling programme to all renewable-energy sources.
Prime Minister Portia Simpson Miller‘s administration has publicly committed to the ambitious goal of 30 per cent renewable energy by 2030. In our view, the Jamaican government has every reason to ensure that Jamaica can meet these targets by allowing all renewable-energy sources to participate in programmes, such as electricity wheeling.
For its own economic development, Jamaica’s Government would be well advised to mandate that the utilities regulation office and the national utility continue and expand ongoing efforts to strengthen Jamaica’s national electricity grid in order to accommodate new, variable renewable generation in accordance with national targets.
In the meantime, however, Jamaica’s electricity generation mix is dominated by diesel and fuel oil – and planned liquefied natural gas capacity – which can be rapidly fired up or down in response to variable renewable generation and changes in electricity demand.
So long as JPS and OUR undertake precautions to address grid congestion, voltage regulation, and other issues associated with distributed generation, Jamaica’s grid should be capable of integrating variable renewable capacity through the wheeling programme.
Commercial and industrial-scale renewable electricity generation is a cost-effective way to meet the Jamaican Government’s renewable energy targets.
Fees should be an incentive
Electricity wheeling should, therefore, include variable-generation capacity in order to promote development of solar and wind-energy technologies at this scale.
For this to be successful, it is critical that regulators assure that fees are reasonable enough to insure that distributed generators will have an incentive to participate in the programme.
Guidance from the regulatory office is also needed to clarify eligibility criteria for a single entity under the wheeling programme. For example, if the Sandals resort chain participates in a wheeling programme, why should it not be allowed to send electricity generated at one resort to another? However, each resort in the Sandals chain is registered as a separate entity, creating uncertainty as to whether such use of the wheeling system would be permitted.
Resolving this issue before electricity wheeling guidelines are finalised will help avoid potential delays and allow ready projects to be implemented on schedule.
As Jamaica’s electricity regulator, it is the responsibility of the utility regulatory office to ensure that the national electricity grid is prepared to accommodate the new renewable electricity capacity – both firm and variable – needed to meet the Government’s 30 per cent target.
Given the high cost of the current petroleum-based electricity system and the country’s strong renewable-energy resources, Jamaica can transition to a secure and reliable renewable-energy system while still reducing electricity costs for consumers.
The Worldwatch Institute is currently finalising a Sustainable Electricity Roadmap for Jamaica that details Jamaica’s abundant renewable energy potential and recommends grid integration and policy solutions for reliably harnessing these resources to help achieve the country’s long-term sustainable energy goals.
Shakuntala Makhijani is a representative of Worldwatch Institute, which is currently working on sustainable energy roadmaps for the Dominican Republic, Haiti, and Jamaica. mkonold@worldwatch.org business@gleanerjm.com

THIS WEEK, Blue Energy, a British company, announced that it will build Africa’s largest solar power plant in Ghana. By the time it is completed in 2015, the 155-megawatt facility will be the fourth-largest power plant in the world and is expected to supply 20 per cent of the Ghanaian government’s target of generating 10 per cent of electricity from renewable sources by 2020.
Apart from being the second-largest producer and exporter of cocoa in the world, Ghana is a significant producer of oil and, in March, Tullow Oil of London stated that an oilfield it found off the coast was a major find. Still, Ghana has made it easy for this US$400-million investment in solar energy to go ahead. The Nzema project will be situated on 183-hectares (about 403 acres) of land in western Ghana. The Ghanaian government has given the investor a100-year lease, as well as planning and connection permission to the 161kV West African Power Pool transmission line, which links Ghana to the Ivory Coast, Togo, Benin and Nigeria.
Int’l investors responded swiftly
The CEO of Blue Energy, Chris Dean, speaking to the
Charlene Stuart, Senior Staff Reporter
Lobby group, Citizens United to Reduce the cost of Electricity (CURE), wants the Office of Utilities Regulation (OUR), to say why it is suspending the non-competitive process for the generation of renewable based electricity.
The electricity generated would be sold to the Jamaica Public Service Company (JPS).
The OUR made the announcement yesterday in a paid advertisement, indicating that the new measures take immediate effect.
The OUR has suspended the processing of non-competitive proposals for the generation of up to 25 megawatts of electricity from renewable energy sources.
The OUR said the suspension will remain until the completion of a competitive tender exercise to procure up to 115 mega Watts of power.
CURE
Technology Minister Phillip Paulwell has announced that starting this week investors in renewable energy projects will be able to bid for up to 115 mega watts of
Technology Minister Phillip Paulwell has announced that starting this week investors in renewable energy projects will be able to bid for up to 115 mega watts of
INVESTORS wanting to build out renewable energy capacity in the latest round of investments in Jamaica will have to do so by early 2015.
Up to 115 megawatts (MW) are up for grabs.
![]() |
Those who are interested to make bids will have to declare that to the Office of Utilities Regulations (OUR) by December 21.
But the request for proposal documents has set tariff caps, which could make investments in certain types of renewables lucrative, but could also mean higher electricity prices to consumers.
What’s more, even with the seemingly fast pace at which the regulator is pushing for renewables to come online