Screen Shot 2015-12-15 at 14.24.13

The Privy Council in London comforts foreign investors.

THE Court of Appeal yesterday gave lobby group Citizens United for the Reduction of Electricity (CURE) final leave to take its fight regarding the Jamaica Public Service’s (JPS) exclusive licence to the UK-based Privy Council.

The appellate court, in March of this year, gave CURE provisional leave to appeal to the Privy Council, Jamaica’s final court of appeal.

Cure is challenging the Court of Appeal decision, in January, to overturn a ruling by the Supreme Court that the JPS’s exclusive licence to provide electricity across the island was invalid.

In October 2012, Justice Bryan Sykes ruled that the exclusive aspect of the 20-year all-island licence, issued by the then energy minister to JPS in 2001, was invalid.

As is the case with most local operations, the National Irrigation Commission (NIC) says energy eats up a large chunk of its operational expenses, with the State-run company spending close to $500 million on electricity in 2014/2015.

This accounted for 40 per cent of its operating costs, and already for this year, the commission’s electricity bill is at 47 per cent of operational costs. “So it is increasing as we bring on additional areas. Once there is a drought, then we have to increase the amount of pumping that is done in each of these districts. In some areas, for some months the electricity cost is greater than the revenue that we generate,” NIC Managing Director Mark Richards explained at yesterday’s

Jamaica Observer Monday Exchange.

The NIC provides irrigation services mainly to the agricultural sector, and to a lesser extent industrial and commercial operations in Yallahs, St Thomas; Rio Cobre and Colbeck in St Catherine; central clarendon; New Forest and Duff House, in Manchester; Braco, Trelawny; Hounslow and Beacon/Little Park, in St Elizabeth; and Seven Rivers in St James

“Our electricity cost is one of the significant challenges that we operate under. We are the second-biggest consumer and payee of the JPS. For the year so far up to October, we are at $330 million. So it’s a challenge [and]we are looking at different energy management strategies and engineering strategies [such as] retrofitting our pumps [and] scheduling of our flows in order to better match the service to deal with the demand,” Director of Technical Services Milton Henry explained.

Henry said the commission faces a peculiar challenge, as while energy prices are trending down, the NIC has to be ramping up its operations to satisfy increasing demand for irrigated water.

“Every system we bring on is contributing to our cost, and we have not been able to pass on those costs to our farmers; so as we partner with them, we are saying let us find some more efficient approaches. We have had quite a bit of success… we have grown our business at a time of major challenges and continue to do so,” Henry said, noting that the NIC’s customer base has doubled from 1,265 in 2006 to 2,349 in 2014.

The NIC has moved to cut down on energy costs by retrofitting 15 of its stations with energy-saving devices. It is also looking to solar and wind energy sources. “So far we did a wind study in Manchester with a view to putting in a five megawatt capacity which would meet a significant portion of our demand. The study has been completed and shows that it is feasible. We are expected to move to the next phase… with some urgency,” he said.

The NIC is also eagerly awaiting the resumption of net billing, which the JPS suspended in May to carry out a review of the two-year pilot programme. The assessment which was conducted by the United States’ National Renewable Energy Laboratory has been completed, but up to last month the energy ministry was not able to tell stakeholders in the solar energy sector exactly when the programme would resume.

Jamaica Observer

 

Lest we forget, Jamaica has been trying to strike deals to migrate to liquefied natural gas (LNG), and failing at it spectacularly, for well over a decade.

It all began four prime ministers ago, when Percival James Patterson was in charge and sought to broker a deal with his counterpart, Patrick Manning, in Trinidad in 2001. And we knew Patterson was serious about the issue, because that time he did not form a committee around it.

Still, it didn’t end well. Trinidad began to waffle – after all, it could get better prices for its fossil elsewhere. Jamaica wanted concessionary pricing for a yearly 1.1 million tonnes of natural gas as a family member in Caricom, but Trinidad was in favour of the hub. Business, after all, is business.

Patterson even put a dedicated man in charge of the LNG programme. That didn’t help. And since then, almost every effort at adding gas to the energy mix has coagulated. You know you have a problem when international headlines pop up asking, ‘Is Jamaica’s Energy Cursed?’

To recap, the actors in Jamaica’s LNG serialised melodrama have included Anthony Hylton, James Robertson, Clive Mullings, Christopher Zacca, Phillip Paulwell, Kelly Tomblin, Exmar, Caribbean LNG, Azurest, Energy World International, Jamaica Public Service Company and now Abengoa SA. Perhaps the only clairvoyant in the mix was Mullings, who, back in 2008, began touting coal as a more practical choice for diluting the viscosity of oil on Jamaica’s balance of payments, given the vagaries of supply in the LNG market.

Not everyone loved the idea. The thought of coal was a bit dirty, and risky, but it wasn’t entirely dismissed. Fracking has now changed that dynamic somewhat.

In 2014, some 13 years since the Patterson-Manning bro-pact and a decade after the more formalised LNG heads of agreement, ESET emerged as the latest reset when current Prime Minister Portia Simpson Miller reached out to an old and trusted ally of Patterson’s – Dr Vincent ‘Head of Kitchen Cabinet’ Lawrence – to bring an end to the confusion that had become Jamaica’s energy policy.

Being a glutton for punishment, Jamaica held on to its LNG ambitions, but also opened up to proposals for coal, compressed gas, and natural liquid gases such as ethane and propane.

Blame it on the cosmos

But even the doc, despite the heavenly moniker that had been bestowed on him in the past, has been no match for the supremacy of Murphy’s law, or whatever it is in the cosmos that appears to want Jamaica to stay wedded to crude. First, the American Ethane/UC Rusal arrangement fell apart – which Lawrence insisted would not derail the 2018 schedule to begin cutting electricity prices – and now there is Abengoa.

Right about now, JPS boss Kelly Tomblin likely has fingers crossed, hoping that New Fortress Energy won’t throw up any surprises; that the arrangement with the American company to supply gas to JPS’ Montego Bay plant will – please, oh please – go right.

General Electric is currently retrofitting Bogue for LNG – a US$22.54-million project that seems to escaped the curse – and Fortress Energy is to start delivering gas by mid-2016. The final terms of the Fortress engagement are now being negotiated.

Before the LNG project was revised from a 360MW single project and split into bite-size pieces under ESET, JPS itself had tried to take on the task under a US$600-million plan that went nowhere. The power utility was said to have a financing revolver lined up but could not secure the gas supplies at the right price.

Under the reset, JPS has two projects to execute – the 120MW Bogue project in Montego Bay for which it has contracted New Fortress, and the 190MW project in Old Harbour Bay. For the latter, JPS reportedly got several bids but chose Abengoa SA, which just days later filed for bankruptcy protection to restructure billions of debt.

Somebody hadn’t done their homework. One would have thought that JPS’s foreign parents Korea East West Power Company and Marubeni – both of which operate in the energy field – would have the temperature of another big energy player. But it appears that they, and the JPS consultants, did not.

Still, Tomblin and team appear to have other options were Abengoa to falter. The Spanish company has four months to right the ship, a timetable that collides with JPS’, which wants to start site prep for the Old Harbour plant by March in order to keep its 2018 commitment. Right about now, JPS is probably reinvestigating the other bidders, hopefully using a different set of consultants than the ones who delivered up the embarrassment of Abengoa.

Old Harbour is an important project for Tomblin, who wants her legacy at the Jamaican utility to be one of transformation. She got a Jamaican power generator and distributor to run, but she wants to leave it as a ‘gas and electric utility’ with a role in developing a regional gas supply hub for the Caribbean market. Old Harbour would be the fulcrum, assuming it gets built.

With Bogue and Old Harbour in play, around a third of base load capacity would be fired by gas, a cleaner and, as important, cheaper fuel source that will allow JPS to produce and supply electricity to the grid at a price below 13 US cents per kilowatt-hour, and knock 1.2 million barrels of oil off the country’s annual orders of crude.

Still, Murphy’s law is tenacious, which means that all Jamaica can do is pray that the stars will finally align in its favour and that the energy gods are in affinity with Vin.

The Gleaner

Jamaica Public Service Company (JPS) claims that switching all its low-consuming users to prepaid meters would increase the risk profile of the utility provider, and secondly, cost it hundreds of millions in lost non-fuel revenue annually – an ironic twist given that the meters are meant to curtail losses.

JPS currently offers prepaid meters in select inner-city areas under a pilot programme, but its admission of the cost puts the timeline for its larger role in question.

“If all customers consuming less than 100 kilowatt hours switched to the prepaid service, JPS stands to lose J$399 million in non-fuel revenues per annum,” the power utility said in its annual tariff application documentation published late last month by its regulator, the Office of Utilities Regulation (OUR).

“By any measure, this exposure is significant and further increases the risk profile of the company, especially given the challenges in meeting certain financial covenants.”

JPS holds US$324 million in long-term loans, and its financial covenants require a minimum undisclosed debt to earnings before interest tax depreciation and amortisation. The company was fully compliant with all its loan obligations as at September 2015.

Customers that consume less than 100 kWh are classified as Rate 10 users. These users usually are low-income households but account for some 222,000 of the 594,000 JPS customers, according to OUR documentation.

Regular customers – Rate 20 – who consume less than 75,000 kWh per month would remain revenue neutral for the switch to prepaid meters.

JPS added that this level of loss is “unsustainable” and is only acceptable for the remainder of the prepaid pilot which offers prepaid meters to a relatively small number of customers. The power utility wants the OUR to increase the prepaid rates to Rate 10 customers in order to remove a large part of that shortfall.

“We would, however, like to state that the rate structure should aim for revenue neutrality as the prepaid programme evolves,” said JPS.

The company proposed an adjustment to non-fuel tariff rates for Rate 10 prepaid customers to $14.4311/kWh for the first 119kWh in a 30-day cycle; and $20.5719/kWh for every kWh above 119kWh in a 30-day cycle.

The OUR rejected that specific JPS proposal. It approved instead a Rate 10 prepaid rate of $13.19/kWh for the first 100kWh in a 30-day cycle and $20.85/kWh for every kWh thereafter for a 30-day cycle.

JPS made US$23.7 million net profit over nine-months ending September 2015 on revenues of US$583 million which nearly doubled the US$12.5 million in profit earned a year earlier.

There was no response to mailed queries and calls to JPS for comment on this story up to press time.

The Gleaner

The oil-fired JPS power plant in Old Harbour Bay, St Catherine is to be converted to LNG.

Spanish firm Abengoa SA has revealed the value of the upgrade and employment prospects for the 190MW power plant project amid pre-bankruptcy filings in its home market.

“The contract for the plant, which will be powered by natural gas and cooled by seawater, is worth more than US$200 million,” said Abengoa in a release.

The engineering and renewable energy firm was selected as preferred bidder by Jamaica Public Service Company (JPS), and the parties are in the process of finalising the contract for the LNG-fired power plant. JPS has said the full project cost would be closer to US$300 million.

Abengoa has about four months in which to secure deals with its creditors and restructure its debts if it is to escape full bankruptcy. JPS has said it is not ready to give up on its preferred bidder just yet, but is monitoring the situation.

Abengoa said it will be responsible for the design, engineering and construction work of the plant that will replace an existing fuel-oil facility and is expected to “create between 300 and 500 jobs during the construction phase”.

JPS wants to decommission the existing fuel-oil plant and move to a natural gas facility to create a cleaner, efficient and more reliable source of power, added Abengoa.

The more than 40-year-old Old Harbour plant remains one of the least energy efficient in the island and its upgrade would form part of the Jamaican Government’s drive to increase cleaner forms of fuel. Jamaica aims to increase renewable energy reliance to 20 per cent of the energy output within the medium term.

SEAWATER COOLING SYSTEM

“The plant will use a seawater cooling system that returns the warm water without adversely impacting the environment. Abengoa’s design will use the existing infrastructure as much as possible, requiring less power and improving the overall output of the plant,” said the Spanish firm in late November, adding that the project would extend Abengoa’s experience in turnkey combined cycle projects to the Jamaican market.

The company informed that it filed for insolvency protection on November 25 before the Mercantile Courts of Seville. The company also indicated that it would continue negotiations with its creditors with the objective of reaching an agreement that ensures the company’s financial viability, “under the protection of Article 5 of the Spanish Insolvency Law”.

The company recorded a €194 million net loss attributable to its parent over nine months ending September 2015 on revenues of €4.87 billion. It holds €6.2 billion in total debt while its earnings before interest tax and amortisation totalled €1.3 billion or 4.5 times net leverage.

Abengoa’s other major combined-cycle projects include the 640MW plant in Centro Morelos, Mexico, and the 440MW combined cycle plant in Portland, Oregon, United States, currently under construction. More recently, Abengoa was awarded two combined cycle plants in Mexico – Nuevo Pemex 680MW, and Norte III, 924MW.

The Gleaner

LIGHT AND power providers, the Jamaica Public Service Company (JPS) said yesterday that it is getting independent advice from its lawyers on whether to proceed with a contract with Spanish firm Abengoa to construct its power plant at Old Harbour, St Catherine.

Kelly Tomblin, the chief executive officer of JPS said yesterday that its shareholders held a conference call with Abengoa to discuss the way forward.

Abengoa’s chief executive Santiago Seage resigned yesterday after it emerged the Spanish renewable energy giant was close to bankruptcy.

The JPS, with the assistance of AMEC Foster Wheeler, a consultancy firm, selected Abengoa whose package consists of general electric combined cycle frame 6B gas turbine. The light and power company was in the process of negotiating a performance contract when the matter of the bankruptcy came to light.

“We were never going to enter into a performance contract until we had some assurance about their financial abilities,” Tomblin said.

She said that December 9 was the deadline for Abengoa to satisfy JPS of its ability to undertake the project and hinted that the light and power company is getting ready to move beyond Abengoa.

“Their problem is that they have some debt coming due but they don’t have the cash to pay. They are going to try to utilise their assets and do other things but that takes too long so we won’t be able to wait out that,” Tomblin said.

The Electricity Sector Enterprise Committee, ESET, said that while it is watching the developments, it is not totally concerned at this point.

Profesor Alvin Wint, a member of the ESET, said that in addition to Abengoa, other entities had submitted detailed bids to construct the power plant and they would be in line to be considered to take on the project.

“We will be requiring that they move quickly and if they need to go to a plan B they go quickly,” Wint said.

Both major shareholders of JPS, Marubeni and Korea East West Power Company Limited have committed to each inject up to 50 per cent of the approximately US$990 million equity that is required to develop the 190 megawatt power plant by year end.

The JPS intends to raise approximately US$210 million in debt funding to help finance the project.

The Gleaner

The JPS power plant in Old Harbour Bay, St Catherine. Ian Allen

Continuous tests as well as monitoring of the construction and commercial operation of the gas-fired 190-megawatt power plant to be developed by Jamaica Public Service Company (JPS) at Old Harbour Bay, St Catherine, have been promised, amid public concerns that the facility could eventually become a health hazzard.

Those health concerns were allayed by environmental consultant Carlton Campbell, who also assured the community in a consultation session Tuesday that they would have a mechanism for complaints for matters that arise when the project gets underway.

The public is weighing in on the environmental impact assessment report, which was done by Campbell’s company, CL Environmental Limited.

Such consultations are a precursor to final consideration and approval of a major project by the central authority, National Environment and Planning Agency (NEPA).

Site preparation for the liquefied natural gas plant is scheduled to begin by the first quarter of 2016 and construction by the second quarter. Commissioning of the plant is expected 22 months later, which would be close to mid-2018 if the current timetable holds.

JPS recently settled on Spanish engineering and renewable energy firm Abengoa to develop the plant, but that selection is now complicated by bankruptcy filings by the company on Wednesday, which is seeking protection in order to restructure its debt of about €9 billion. Spanish law gives it four months to strike deals with creditors under ‘pre-insolvency’ proceedings and avoid full bankruptcy.

The size of the contract to Abengoa was not disclosed, but previous reports say the project could cost around US$200 million to US$300 million. CL’s environmental impact report indicates that capital expenditure for construction of the plant is US$219.5 million, but last night JPS clarified that this figure related to equipment only. The utility said the full project cost would end up closer to US$300 million.

Deliver power supplies

The new plant will retire old capacity at Old Harbour, and is expected to deliver power supplies to the national electricity grid at less than 13 US cents per kilowatt-hour. The current plant is oil-fired.

Old Harbour residents were told to expect intermittent traffic disruptions and longer commutes, as well as increases in the cost of travel once the 190MW project enters the construction phase.

Campbell said the expected noise levels were compliant with the night and daytime standards of NEPA and the World Bank, and that water and air quality as well as drainage and wastewater systems would be monitored continuously.

“There is a perception that there will be health implications from this new plant,” said Campbell, while ticking off a list of reported concerns that included respiratory problems, increased noise levels, pollution, vibration and soot emissions.

However, he said, a health impact study was conducted which showed that residents would not be affected.

The environmental consultant also said the natural gas emissions and effluent released from the plant were not expected to harm the fish stock on which a lot of residents of the village depend for their livelihood.

The plant is expected to employ 400-450 during construction, and 45 persons permanently at commissioning.

The project was submitted to NEPA for approval on September 2, 2014, and after initial review, the agency requested that JPS produce an environmental impact report. The report was submitted at the end of October and is under review by various agencies.

Their feedback will eventually be communicated to JPS.

“The agencies will therefore refrain from making any comments or answering any questions in relation to the development at this time, as the application is currently the subject of review,” said NEPA official Ruth-Ann Lacey-Sherrard at Tuesday night’s public consultation.

The presence of the agencies at the event, she said, was merely to observe and take note of public comments that would inform the deliberations of the Natural Resources Conservation Authority (NRCA) which is a division of NEPA.

“Please note, carefully, that the final decision on the application is the sole responsibility of the NRCA,” Lacey-Sherrard said.

“The agencies’ review of the public presentation and consultation processes is extremely important in the decision-making process. These consultation processes provide an additional opportunity for stakeholders to air their concerns, make comments, provide opinions and views on the development project, and afford the applicant the opportunity to address these,” she said.

The Gleaner

JPS to open discussions with other renewable vendors

The Jamaica Public Service (JPS) yesterday announced that it will be engaging in discussions with other renewable vendors to ensure execution of the planned energy 190 MW Power Plant in Old Harbour, St. Catherine.

Chief Executive Officer, Kelly Tomblin in a press release advised the public that Spanish renewable energy and engineering firm Abengoa has filed for protection from creditors – an initial step towards filing for bankruptcy. The company was recently announced as the preferred bidder to construct the combined-cycle plant in Old Harbour.

“While JPS notes the development with regret, it is fully prepared to activate its alternative plans to ensure the execution of the project, which will replace the present Old Harbour Bay Power Station, while adding more Liquefied Natural Gas to the country’s energy mix,” Tomblin stated.

“We will be having dialogue with Abengoa — but JPS remains undaunted by the news. As a responsible corporate entity, our company has been in full preparation mode for any type of challenge regarding the completion of this project. We will not be derailed from our mission to bring real change to the energy sector and by extension, to Jamaica,” she continued.

The CEO reportedly stated that JPS has been eyeing other vendors since the announcement of the Abengoa’s financial situation.

Abengoa, which reported debt of ¤8.9-billion in its third quarter financials, began bankruptcy protection proceedings to avoid what could be one of Spain’s largest insolvencies.

The figure could be doubled when including ¤2.1 billion in funds it owed to suppliers and ¤5.9 billion of debt the company has in subsidiaries it said could potentially be sold. According to reports, the company has filed for protection from creditors with hopes of reaching a deal on its debts by March.

According to Tomblin, Abengoa was selected based on its wide ranging and impressive technical expertise. The company has been touted as one of the world’s top builders of power lines transporting energy across Latin America and a top engineering and construction business, making massive renewable-energy power plant.

The light and power company also had the understanding that Abengoa’s financiers were committed to the company for the long term.

“JPS wishes to assure its customers and all stakeholders that the 190 MW project remains on track for the plant’s commissioning in 2018.The Company will keep stakeholders informed as events unfold,” she said.

Jamaica Observer

 

Although Abengoa, the Spanish company selected as the preferred bidder to build a major power plant in Jamaica, has initiated steps that could lead to a bankruptcy declaration, Jamaica Public Service Company CEO Kelly Tomblin is not yet ready to call it quits on the multinational corporation.

Reacting to news of the bankruptcy proceedings initiated by Abengoa, Tomblin said she was monitoring the situation of the Spanish renewable-energy company.

It was only last week that JPS announced Abengoa as the preferred bidder to build the 190-megawatt combined-cycle plant in Old Harbour, St Catherine.

Despite fears that Abengoa may not be able to fulfil the requirements of the bid, given its precarious financial situation, Tomblin is holding out hope that the company will be able to make good on its financial obligations in relation to the bid.

“We have been monitoring the situation for some time. We have backup plans, but we have to wait and see what Abengoa shows us. But pot can’t call kettle black because JPS, as you know, has had its own financial difficulties, and we are just now emerging from those, so we know what it’s like, so we want to make sure that we don’t overreact,” Tomblin told The Gleaner last evening.

In the event that Abengoa folds completely, Kelly Tomblin pointed out that JPS has several alternatives.

“There are other vendors. We have many vendors who were poised to build the plant, so if, in fact, Abengoa can’t show, then other people can build the power plant. As you know, we have shareholders who have deep expertise, but we don’t want to jump the gun. Of course, Abengoa will have to give us financial assurance, but, again, pot can’t call the kettle black. It wasn’t very long ago that JPS, too, was facing insolvency problems,” she said.

Energy Minister Phillip Paulwell, in reacting to the news, said there was no need to panic and that JPS should be given the space to continue the procurement process.

When asked if the situation vindicates him in respect of the Energy World International (EWI) bid, Paulwell said, “There will be vindication when the gas is here because that, for me, is the most important aspect.”

Paulwell was in charge of overseeing the Government’s 391-megawatt project, which awarded a bid to EWI, a company which faced financial woes, leading to questions about its ability to deliver on the bid. This was before responsibility for the project was handed over to the Vin Lawrence-led enterprise team.

Now, with news of Abengoa’s bankruptcy filing, Jamaica’s renewable-energy plans may be delayed yet again.

Abengoa’s latest financial woes sent shockwaves through the banking sector and financial markets in Spain yesterday, fuelling concerns that the country’s lenders may be left with heavy losses.

According to international media reports, Abengoa has been having financial challenges from as far back as 2013, when Spain instituted energy reforms, which reduced subsidies to renewable-energy providers. This affected Abengoa’s capital base significantly and further exacerbated its pile-up of debt.

The Financial Times has said that a possible default by Abengoa could count as the largest bankruptcy in Spanish history, given that as of September, Abengoa carried gross debt of £8.9 billion.

The filing for preliminary creditor protection yesterday came after a potential investor cancelled plans to inject £350 million into the company.

While he could not comment on questions of whether due diligence was done on the Abengoa bid, Private Sector Organisation of Jamaica CEO Dennis Chung said news of the filing does not mean the company will go under, as bankruptcy proceedings often give a company an opportunity to rebuild.

“I couldn’t comment on due diligence. I have to believe that proper due diligence would have been done, so that question should be put to the person who actually did the due diligence,” Chung said.

 

The Gleaner

* Abengoa has 4 months to reach deal with creditors

* Shares plummet 54 pct, bonds virtually worthless

* Abengoa’s bankruptcy would be Spain’s largest on record (Adds Abengoa removed from Ibex, details on company)

MADRID, Nov 25 Spain’s Abengoa started insolvency proceedings on Wednesday after a potential investor said it would not inject fresh capital into the energy firm, sending its share price tumbling by 54 percent.

Under Spanish law, companies can enter into pre-insolvency proceedings, giving them up to four months to reach an agreement with creditors to avoid a full-blown insolvency process and a potential bankruptcy.

Failure by Abengoa to reach such a deal could lead to Spain’s largest bankruptcy on record. The company employs around 24,000 people worldwide.

Spanish and international banks’ total exposure to Abengoa stands at around 20.2 billion euros ($21.4 billion), including financing for projects, a source familiar with the matter said at the end of September.

The Seville-based engineering and renewable energy firm, which has biofuel and solar-heated power plants in the United States, has been struggling for a year with high debts but the situation became unsustainable in July. It first cut its 2015 targets and stepped up an asset sales plan on July 31, only to announce a share issue days later.

Since then, the company’s market value has tumbled by around 85 percent, hit by uncertainties over whether creditor banks would agree to back the issue.

The shares plummeted by 69 percent when trading resumed following a more than three-hour suspension on Wednesday morning. They closed down 54 percent, wiping out around 470 million euros in market value on the day.

The stock market operator said Abengoa would be removed from Spain’s blue-chip index Ibex as of Nov. 27.

Bonds also lost most of their value.

Abengoa earlier confirmed that Gonvarri, a unit of privately-held industrial group Gestamp, had backed away from a plan to inject around 350 million euros into the firm.

“The company will begin the negotiating process with its creditors with the aim to reach an accord to guarantee the financial viability under the Article 5 of the Bankruptcy act, which the company intends to request as soon as possible,” Abengoa said in a statement.

Abengoa has been trying to find new investors since early August, when it announced a 650 million euro rights issue of new shares to cut gross debt of some 8.9 billion euros.

Gonvarri’s interest was conditional on banks underwriting the issue and it had asked the banks to inject 1.5 billion euros in to the company, sources told Reuters late on Tuesday.

Earlier this month, Abengoa’s auditor Deloitte said the group faced significant risks and its future depended heavily on the proposed investment deal with Gonvarri.

https://solarbuzzjamaica.com/jps-announces-preferred-bidder-for-old-harbour-plant/

Reuters.com