The Jamaica Public Service Company Ltd (JPS) has officially concluded work to convert the Bogue Power Plant in Montego Bay, St James, to dual fuel capability.

The plant is now able to use natural gas, as well as automotive diesel fuel, which it has been using since its commissioning in 2004. The work, which started in January of this year, was completed on April 26, on time and within budget, at a cost of US$22.7 million or J$2.7 billion.

The arrival of liquefied natural gas, which is being undertaken by US-based New Fortress Energy, is expected by August of this year, at which point the newly converted Bogue Power Plant will begin to use the more environmentally- friendly fuel. The multimillion-dollar project will add significantly to the country’s energy diversity, fuel security, flexible generation, and production of clean energy.

Senior Vice-President of Generation Joseph Williams notes: “This is just the first phase of a deepening fuel diversification process which is taking place at JPS. We are excited to be a leader of this revolutionary move, which will not only see a more diverse energy landscape, but also possibilities for the commercial and transportation sectors of our country.”

The Bogue Combined Cycle Power Plant produces 120MW of the country’s average daily use of over 600MW of electricity.

 

The Observer

The JPS power station at Bogue, Montego Bay.

The Jamaica Public Service Company (JPS) said it expects to complete the conversion and upgrade of the Bogue combined-cycle power plant in Montego Bay, St James, within a week.

The US$22-million ($2.5-billion) project kicked off in January and, when completed, it will be able to operate on either liquefied natural gas (LNG) or its current fuel source, automotive diesel oil.

JPS said it will be buying natural gas under a long-term supply agreement from Fortress New Energy and expect to start receiving the product within the next four to six months.

JPS indicated that Bogue would be ready by the end of the second week in May in an email to the Financial Gleaner.

The company said New Fortress “is responsible for all activities associated with delivering the LNG to the port in Montego Bay, storing the LNG in tanks, regasifying the LNG and delivering it by pipeline to our power plant at Bogue”.

The project to convert the Bogue power plant, which is being undertaken by General Electric, kicked off on January 11 this year.

The work involves removal of a gas turbine and heat recovery steam generator from service, which was expected to clear the way for General Electric to start installing equipment.

JPS said the project would add significantly to the country’s energy diversity, fuel security, flexible generation and production of clean energy.

New Fortress Energy began developing its terminal and pipeline at the Montego Freeport at the end of last year, but JPS has no stake in that project.

mcpherse.thompson@gleanerjm.com

 

The Gleaner

The oil-fired JPS power plant in Old Harbour Bay, St Catherine is to be replaced with a gas-fired plant.

Jamaica Public Service Company (JPS) says the National Environment and Planning Agency (NEPA) has approved the construction of the 190-megawatt gas-fired power plant at Old Harbour Bay, St Catherine.

The Office of Utilities Regulation and the Electricity Sector Enterprise Team have also given formal approval of the power purchase agreement for the new facility, the power utility said.

JPS President and CEO Kelly Tomblin said the utility was now finalising details of the project with equipment supplier General Electric Corp, and engineering procurement and construction company Power China. The latter company has been contracted to build the plant.

The arrangements for the project are to be finalised within the next two weeks.

JPS’ disclosure of the project approval follows its weekend announcement, via a posting on its website, that it had finalised an agreement with New Fortress Energy to supply the Old Harbour plant with natural gas.

“We are now at an advanced stage in relation to closing the financing of the project, which we expect to be completed by the end of April,” said the JPS chief executive.

New Fortress is also the utility’s gas supply partner for the power plant at Bogue in Montego Bay.

The Old Harbour plant will be a brand new facility. Once built, JPS plans to dismantle the current oil-fired plant at Old Harbour and return the site to brownfield status.

“We anticipate that this new power plant will be generating electricity at below 13 US cents per kWh when it comes on line, which is remarkable, given the necessity to build new infrastructure and bear the transportation and other logistic costs,” Kelly said.

The timelines for the project were laid out during last November’s public consultations on the environmental impact assessment report.

JPS said yesterday that there are no changes to the timeline for site preparation for the liquefied natural gas plant, which is scheduled to begin in the first quarter of 2016, giving the utility just days to hit that deadline.

Construction will begin by the second quarter and the plant’s commissioning is expected by July 2018.

JPS entered into a memorandum of understanding in December 2015 with a Chinese company, now identified as Power China to build the 190, megawatt plant.

The Chinese company replaced the Spanish engineering and renewable energy firm Abengoa, which filed for bankruptcy protection just days after striking a deal with JPS.

The Jamaican utility reaffirmed on Wednesday that the 190MW project is expected to cost around US$300 million.

The gas component, which includes development of a terminal and pipelines to the JPS plant, is a separate project to be undertaken by New Fortress. The arrangement is similar to that agreed for the Bogue plant.

JPS also already had dealings with General Electric, which is converting the diesel-fired Bogue plant to a combined cycle operation to burn either diesel or LNG.

The conversion is costing JPS US$22.74 million or about $2.7 billion, and is scheduled to wrap up by midyear.

Gleaner

The JPS power station at Bogue, Montego Bay, which is being converted to run on LNG.

New Fortress Energy, the company seeking to supply liquefied natural gas (LNG) to Jamaica, has secured a two-year contract for an LNG vessel and is to start shipping gas this month.

Golar LNG Limited, a Bermuda-registered company which operates the vessel Golar Artic, revealed the contract details to its investors.

“Golar has now concluded a two-year charter agreement with New Fortress Energy Transport Partners LLC (NFE) for the employment of Golar Arctic in Jamaica,” said Golar its statements obtained by the Financial Gleaner.

New Fortress has an agreement with Jamaica Public Service Company (JPS) to supply gas to its 120MW power plant at Bogue in Montego Bay, a contract New Fortress will service via gas infrastructure under development at the Montego Bay port. JPS has been mum on the price at which the gas will be supplied to Bogue.

The American company is also expected to develop gas infrastructure and supply JPS’ Old Harbour plant with LNG once it is built, but those negotiations continue.

Bogue is currently being converted to run on gas as well as diesel oil, the fuel on which it was originally commissioned in 2003. General Electric is doing the retrofitting under a US$22.74-million contract from JPS. Bogue will become a combined-cycle plant, capable of switching between gas and diesel.

New Fortress Energy assumes the costs for delivering gas to the burner tip. JPS has no stake in the gas infrastructure project.

New Fortress’ ambition Golar said the deal it has with New Fortress solves a long-standing problem regarding the cost of regasification, and that it fits with New Fortress’ ambition to become a regional supplier of LNG to Caribbean countries.

“Jamaica has long sought to replace liquid fuels with LNG, however, the size of the market has always made it difficult to justify the cost of a conventional floating storage and regasification unit,” said the fuel shipping company.

“New Fortress have now solved this challenge by utilising ship-to-ship transfer of LNG from Golar Arctic on to smaller LNG carriers to service a number of locations within the country of Jamaica.”

Golar Arctic is scheduled to load the first LNG cargo in support of this new business “during March 2016”. Golar and New Fortress believe this new approach to delivering LNG to niche markets has wide application within the Caribbean and other similar markets around the world, stated Golar.

“New Fortress have, with their entrepreneurial approach to business development, shown that downstream LNG markets can be developed within a much shorter time frame than is customary. Similar fast-track solutions will be essential if consumers are to benefit from the large incremental volumes of LNG that will be delivered to market over the next three-four years,” stated Golar.

The Financial Gleaner sought a project update from both JPS and New Fortress, but none came up to press time.

Golar LNG this week reported a fourth-quarter adjusted operating loss of US$35.9 million.

The Gleaner

The oil-fired JPS power plant in Old Harbour Bay, St Catherine is to be replaced with a gas-fired plant.

The announcement of an agreement between Jamaica Public Service Company (JPS) and a Chinese firm is expected this week for the construction of the new energy plant at Old Harbour.

JPS and American company New Fortress Energy are executing separate projects at Old Harbour – the Jamaican utility company is building a new 190 MW plant, while Fortress is financing and developing the gas infrastructure to supply the plant with LNG.

Together, the projects are estimated at around US$500 million.

JPS said it will have no ownership in the gas infrastructure project nor contribute to the cost of developing it, but will solely be a client of New Fortress, which will build its pipeline to connect to the JPS plant. The same arrangement applies to the gas infrastructure under development by New Fortress in Montego Bay, which will feed gas to JPS’ Bogue plant.

The utility company said previously that the 190 MW combined cycle plant at Old Harbour is expect to cost close to US$300 million.

The name of the Chinese contractor will be disclosed only after the deal to develop the plant is finalised, JPS said. The utilitycompany had previously chosen Abengoa to develop the plant only to be embarrassed when the Spanish firm filed for bankruptcy protection in its home country just days later.

JPS is also in final negotiations with General Electric (GE) as the primary equipment supplier for the Old Harbour plant.

“JPS is currently finalising the agreements with both GE and the ‘EPC’ contractor and coordinating the start of this new generation facility with the completion of an associated LNG facility that will be built to provide gas. These two projects will total over US$500 million and begin operation in early 2018 with full commercial operation by the middle of 2018,” said JPS via email.

EPC is a categorisation, which stands for ‘engineering, procurement and construction’ contractor.

The plant’s advance GE turbines will utilise cleaner burning natural gas, replacing the heavy fuel oil currently used at Old Harbour, and will be able to integrate increased solar, wind and hydro resources as Jamaica moves towards producing more electricity from renewable resources.

“GE will provide four turbines – three gas turbines and one steam turbine the three heat recovery steam generators, the four electrical generators and the major controls,” said JPS.

Once the new Old Harbour plant is built, the current structure will be dismantled, and the property will resort to brownfield status, according to JPS spokeswoman Winsome Callum.

New Fortress is negotiating separately with the Electricity Sector Enterprise Team regarding its gas project, Callum said.

JPS has spent some US$4 million so far in preparing for the upgrade over the past 24 months.

The  Gleaner