Kelly Tomblin, president of Jamaica Public Service Company. - Ian Allen / Photographer
Kelly Tomblin, president of Jamaica Public Service Company. – Ian Allen / Photographer

Power distributor Jamaica Public Service Company (JPS) remains committed to using liquefied natural gas (LNG) for its planned 360-megawatt power plant despite Government’s expected plan to scrap the supply of gas for the project, according to the utility’s boss.

The private sector can assume the role of supplying the gas, if allowed by Government, JPS Chief Executive Officer Kelly Tomblin said Tuesday.

The company will meet with Government this week to determine its next step.

“The private sector could secure LNG if Government permits it,” Tomblin told

Kelly Tomblin, president of Jamaica Public Service Company. - Ian Allen / Photographer
Kelly Tomblin, president of Jamaica Public Service Company. – Ian Allen / Photographer

Power distributor Jamaica Public Service Company (JPS) remains committed to using liquefied natural gas (LNG) for its planned 360-megawatt power plant despite Government’s expected plan to scrap the supply of gas for the project, according to the utility’s boss.

The private sector can assume the role of supplying the gas, if allowed by Government, JPS Chief Executive Officer Kelly Tomblin said Tuesday.

The company will meet with Government this week to determine its next step.

“The private sector could secure LNG if Government permits it,” Tomblin told

There’s a warning that Jamaica could suffer some fallout in the international investment community arising from the Government’s decision to change plans for the implementation of the multi-billion dollar liquefied natural gas, LNG project.

According to Opposition Spokesman on Energy, Gregory Mair, the country’s image will be tarnished in light of the fact that an international company had been selected for the project.

In July, Korean conglomerate Samsung Corporation was declared the preferred bidder for the development and operation of

It is high time the Simpson Miller administration end the pussyfooting and come clean on the liquefied natural gas (LNG) project. For its policy-by-dribble is both confusing and confidence-draining and risks doing grave damage to the Jamaican economy.

First, let us place things into perspective. It is our view that alongside credible fiscal policies – which, hopefully, are being sorted out in current negotiations with the International Monetary Fund (IMF) – energy is the potential economic game-changer for Jamaica.

With the domestic price of electricity at upwards of US$0.41 per kilowatt-hour, Jamaican firms are difficultly placed to effectively compete with hemispheric and global manufacturers and service providers. Indeed, the higher price of energy has been a significant contributor to this country’s long period of anaemic advance in GDP.

A substantial part of our problem, of course, is that the bulk of our electricity is generated by old, inefficient power plants that burn expensive oil. Changing the fuel mix, therefore, is a critical component towards reducing the cost of domestic energy.

Settled on natural gas

For more than a decade, Jamaican administrations have deliberated on the issue and appeared, in the end, to settle on natural gas as the fuel of choice.

It is largely against this backdrop that the former Jamaica Labour Party administration, after a badly compromised initial tender process that it was forced to overturn, called for new bids for an LNG storage and regasification facility to begin to give effect to the fuel-conversion programme. Months ago, it was announced that Samsung was the preferred bidder for that facility.

Previously, the Jamaica Public Service Company, an electricity generator and monopoly distributor of power, won the bid to establish a natural gas-burning, 480-megawatt power plant. The expectation was that with natural gas and enhanced efficiency, this facility would drive down the cost of power by a third – not sufficient, but a start.

This newspaper has always felt, and argued, that coal, and other fuels, ought to be part of the energy mix. Our primary concern is for the delivery of the cheapest power to afford the economy a fighting chance at competitiveness. At the same time, we want to be assured of a predictability of supply, starting with the fuel.

Project could be sidelined

Unfortunately, the Government‘s poor communications strategy is injecting grave uncertainty and potential partisan rancour into the discourse.

Dr Carlton Davis, the highly respected public servant who heads the Government’s energy task force, had hinted that the LNG project could be sidelined if the Samsung bid did not meet specific price points for the delivery of electricity. It has for weeks been leaking out that those price points, whatever they were, have not been met and that LNG might be abandoned.

What, precisely, this means remains unclear. We would, for instance, wish to be told frankly whether Jamaica can find no supplier of LNG – the price of which has risen on the back of demand in Asia despite the collapse of the price of natural gas in North America – at a cost that makes sense. Or whether it is other elements of the pricing of the project that don’t compute, and which party they relate to. Or, perhaps there is another approach to the project, including a mix with other fuels.

Uncertainty, ultimately, breeds apathy.

The opinions on this page, except for the above, do not necessarily reflect the views of The Gleaner. To respond to a Gleaner editorial, email us: editor@gleanerjm.com or fax: 922-6223. Responses should be no longer than 400 words. Not all responses will be published.

Read more:

Concern is mounting about the medium-term effects of a reported decision by the Government to change plans for the implementation of the multi-billion dollar liquefied natural gas, LNG, project.

Some members of the small business sector feel their operations will crumble if they continue to depend exclusively on the Jamaica Public Service Company, JPS, for electricity.

Chairman of the Energy Committee of the Medium Small and Micro -sized Enterprises, MSME, Alliance, Anthony Morgan, states that his members are in a state of limbo based on the report, and need clarification from the Government.

He explains that changes need to come soon or many jobs will be lost.

Read more:

Concern is mounting about the medium-term effects of a reported decision by the Government to change plans for the implementation of the multi-billion dollar liquefied natural gas, LNG, project.

Some members of the small business sector feel their operations will crumble if they continue to depend exclusively on the Jamaica Public Service Company, JPS, for electricity.

Chairman of the Energy Committee of the Medium Small and Micro -sized Enterprises, MSME, Alliance, Anthony Morgan, states that his members are in a state of limbo based on the report, and need clarification from the Government.

He explains that changes need to come soon or many jobs will be lost.

Read more:

Prime Minister Portia Simpson Miller and Energy Minister Phillip Paulwell.-file
Prime Minister Portia Simpson Miller and Energy Minister Phillip Paulwell.-file

Lower light bills not coming anytime soon

Arthur Hall, Senior News Editor

The Sunday Gleaner has now confirmed that the Portia Simpson Miller-led administration will announce plans to abandon its long-stated intention to introduce liquefied natural gas (LNG).

After years of planning and millions of dollars in expenditure, the Simpson Miller administration has decided that it just cannot afford the cost of setting up the infrastructure and other requirements for the introduction of LNG.

Energy Minister Phillip Paulwell is scheduled to make that announcement early next month, but government sources say a new plan could be announced at that time as Paulwell continues his desperate push to reduce electricity bills.

“I can say that the numbers are not adding up,” a government source told The Sunday Gleaner late last week.

“As you would have suspected, we knew this was a likely outcome for some time now and had begun to support the offtakers (electricity and alumina producers) to rev up plans ‘B’ and ‘C’, and they are so doing,” added the source who asked that his name be withheld.

It is expected that plans ‘B’ and ‘C’ would see the Jamaica Public Service Company (JPS) being allowed to establish the LNG infrastructure and source the gas for the multibillion-dollar plant it plans to construct in Old Harbour, St Catherine.

The JPS would also sell LNG to the alumina producers which have long argued that the high price of electricity in Jamaica makes production uncompetitive.

“We have long told the Government that the introduction of LNG should be private sector-driven, but the People’s National Party administration before it lost the 2007 general election was adamant that it should be state-controlled and the Bruce Golding-led Jamaica Labour Party government followed that path,” said a source in the energy sector last week.

“If this was a private sector-led drive, EXMAR would have started construction in 2009 and, by this year or early next year, the country would have LNG and lower electricity bills,” added the source who asked not to be named.

Last year, The Gleaner first reported that a November 2010 report by a World Bank-recommended team of consultants suggested that the Government put on hold its plan to introduce LNG.

uncertainty with project

At the time, the consultants stated that there was ambiguity and uncertainties surrounding several aspects of the project which could make it a financial disaster for the Government.

According to the consultants, a focused economic and financial feasibility study should be completed quickly before a final design specification for the Floating Storage and Regasification Unit and pipeline system.

The consultants also warned that the Government could be exposed to great financial risk for future gas purchase.

But then Energy Minister James Robertson and members of the LNG Steering Team scoffed at the consultants’ report as they responded to the queries.

“That (consultants’) assessment report raised several valid questions of the project, for which comprehensive answers were provided,” Robertson told The Gleaner at the time.

Nedburn Thaffe, Gleaner Writer

Plans by the Government to scrap the liquefied natural gas (LNG) project, which was part of measures to diversify the country’s energy mix and cut electricity cost, are threatening to throw the business sector into disarray.

Yesterday, president of the Private Sector Organisation of Jamaica (PSOJ), Christopher Zacca, noting that the introduction of LNG was backed by his organisation, said there was now “concern” over the report carried in The Sunday Gleaner yesterday.

As such, Zacca said, he would be calling a meeting of the PSOJ energy committee in short order to have discussions on the matter.

The Sunday Gleaner indicated that Energy Minister Phillip Paulwell is scheduled to announce next month the intention of the Government to do away with the project.

Gleaner sources say the Government is likely to revert to plans B and C, which will see the Jamaica Public Service Company (JPS) being allowed to establish the LNG infrastructure and source the gas for the multibillion-dollar plant it plans to construct in Old Harbour, St Catherine.

Trouble for sector

Opposition Spokesperson on Energy Gregory Mair, when contacted yesterday, said the report spells trouble for the country’s energy sector.

“This matter that we have been stuck with heavy fuel oil is not good news at all,” he said before chiding the Government for its handling of the project.

“I don’t know what went wrong but the bottom line is that it was going to be the private sector that was going to be funding the entire LNG project and I think they just messed up the whole thing,” Mair said.

In the meantime, yesterday, president and CEO of JPS, Kelly Tomblin, said her company intends to go ahead with plans to build its multibillion-dollar plant in Old Harbour, St Catherine, but added that the shape of the development would be dependent on how the Government now intends to participate in the project.

She added that she was looking forward to meeting with Paulwell in the coming week to discuss the way forward.

The Gleaner understands that Paulwell is currently off the island and is expected to return tomorrow.

nedburn.thaffe@gleanerjm.com

Read more: http://jamaica-gleaner.com/gleaner/20120924/lead/lead6.html