Consulting engineer Howard Chin is making the case for the Alpart plant, which was recently acquired by Chinese firm Jiuquan Iron and Steel Company Ltd (JISCO), to be operated entirely using renewable energy.

JISCO has announced plans to invest US$2 billion to expand the plant which will see the addition of an aluminium smelter powered by a coal-fired plant.

Chin has, however, argued that the heat that would be generated from the coal-fired plant could be detrimental to aquatic, plant and animal life in and around the Black River area, and as such, renewable-energy sources should be considered.

“Cooling the power plant and running the bauxite refinery requires a lot of water. How hot would the Black River become downstream of Alpart? Hot enough to kill animal life? Certainly, NEPA (National Environment and Planning Agency) is not answering these questions which have to be answered. Nor do they have the technical capability to do so,” Chin said in an emailed response to The Gleaner.

STORAGE POWER PLANT

In recognition of the problem of storage capacity associated with renewables, Chin explained that a large pumped hydroelectric storage power plant could be used to power the alumina plant in the first instance.

“It could be done using a large renewable energy system backed up by a pumped storage system,” he said.

Pumped hydroelectric storage facilities store energy in the form of water in an upper reservoir, pumped from another reservoir at a lower elevation. During periods of high electricity demand, power is generated by releasing the stored water through turbines in the same manner as a conventional hydropower station. During periods of low demand, the upper reservoir is recharged by using lower-cost electricity from the grid to pump the water back to the upper reservoir.

Turning his attention to the Bayer Process, which would be used to produce aluminium should the Chinese go ahead with plans to build a smelter at Alpart, Chin observed that the heat given off could be transferred to the alumina refinery, which requires it in large quantities. According to the former Jamaica Institution of Engineers president, the smelter could also be powered by renewable energy.

“The alumina refinery needs a lot of heat. The aluminium smelter needs electricity and ends up giving off a lot of heat. Frankly, it might be possible to run the combined alumina and aluminium refining plant on a mostly very large renewable-energy system and a very large pumped storage system, and moving the heat from where it is produced to where it is needed,” he said.

Gleaner

An explosion that killed at least 21 people and injured five others last Thursday at a coal-fired plant in central China has not gone unnoticed by consulting mechanical engineer Howard Chin.

He has argued that the incident should give the Jamaican authorities cause for pause with regard to a proposal from the Chinese to build a 1,000-megawatt coal-fired plant at the Alpart alumina refinery which has been acquired by Chinese firm Jindal Iron and Steel Company Ltd (JISCO).

“China has a reputation for explosions at its coal-fired plants because the safety standards are not very well regulated, so Jamaica could face that risk … . If you look at the North-South Highway, the Chinese did a quick slab job on that one. They didn’t do proper studies for that project, if you ask me. So I think these coal plant explosions in China should be instructive for Jamaica,” he said in an interview with The Gleaner.

Chin, who is a former president of the Jamaica Institution of Engineers (JIE), explained that explosions in coal-fired plants are generally caused by improper welding.

According to Chin, the fact that the Chinese do not adhere to international welding standards, for the boiler and pressure vessels that would be used in the coal-fired plant, established by the American Society of Mechanical Engineers (ASME) that could result in improper welding. And improper welding could lead to deadly explosions, similar to those that occur in China. A lack of sufficient ASME certified welders in Jamaica is also seen as problematic.

 

CAUSE OF THE FIRE

 

Last Thursday’s explosion at the coal-fired plant in the Hubei Province of China was caused by a faulty high-pressure steam pipe which went bust. The Dangyang-based plant was still under construction when the explosion occurred.

The former JIE president raised further questions about what he described as a number of defects that would be associated with the proposed coal-fired plant.

“There is the matter of the ash. Where are you going to put all the ash? It’s possible you can put it all in cement, but that would require a cement plant to be built to take all that ash, because of lot of ash will be generated. There is also cooling water that will be needed, and the only water source that is near there is the Black River and if you cool the plant using the Black River, you are going to kill the fish in that river with all the heat, so I don’t think that is a good idea,” he said.