The Office of Utilities Regulation (OUR) says it will ensure that power utility Jamaica Public Service Company does not increase bills to consumers based on the delay in the delivery of cheaper gas fuel.

The first delivery of liquefied natural gas – LNG – by JPS’ supplier was expected in April, but has been pushed back to August.

New Fortress Energy has developed a terminal in Montego Bay to feed gas to JPS’ Bogue plant, which has been converted to burn either LNG or automotive diesel oil.

“The OUR has moved to assure consumers that it will be vigilant in ensuring that the delay in the delivery of liquefied natural gas to the Bogue power plant will not result in an increase in the price of electricity,” said the regulator in a statement.

While welcoming the completion of the conversion of the 120-megawatt combined cycle plant, the OUR signalled disappointment with the “four-month delay” in the delivery of the overall project.

The gas supply agreement signed by JPS and New Fortress Energy on August 5, 2015, stipulated that gas delivery would commence April 2016, the OUR stated.

“Safeguards for customers were included in the agreement with New Fortress to ensure that any delay on its part would not result in negative cost implications for customers,” noted OUR Director General Albert Gordon. “The OUR has been monitoring the project closely and will continue to keep the public abreast of its progress.”

Project’s goal

The Bogue project’s goals, which are aligned to those in the National Energy Policy, were to reduce fuel cost, and lower the operations and maintenance expenditure of electricity generation. Gordon noted that the OUR’s involvement in the project began in 2008 and that the agency mandated that the plant be upgraded to burn gas in the 2014-2019 JPS tariff determination.

“To ensure this, the OUR also made provisions for the setting up of the Bogue Plant Reconfiguration Fund (BPRF), financed through the tariff, to facilitate the conversion cost,” the agency said.

The revenues for the BPRF – which totalled $15 million – were collected by the JPS through a line item in the monthly fuel rate calculation on customers’ bills, over a twelve-month period, between February 2015 and January 2016, the OUR said.

Requests to JPS for comment were unanswered up to press time.

The Gleaner

The JPS power station at Bogue, Montego Bay.

The Jamaica Public Service Company (JPS) said it expects to complete the conversion and upgrade of the Bogue combined-cycle power plant in Montego Bay, St James, within a week.

The US$22-million ($2.5-billion) project kicked off in January and, when completed, it will be able to operate on either liquefied natural gas (LNG) or its current fuel source, automotive diesel oil.

JPS said it will be buying natural gas under a long-term supply agreement from Fortress New Energy and expect to start receiving the product within the next four to six months.

JPS indicated that Bogue would be ready by the end of the second week in May in an email to the Financial Gleaner.

The company said New Fortress “is responsible for all activities associated with delivering the LNG to the port in Montego Bay, storing the LNG in tanks, regasifying the LNG and delivering it by pipeline to our power plant at Bogue”.

The project to convert the Bogue power plant, which is being undertaken by General Electric, kicked off on January 11 this year.

The work involves removal of a gas turbine and heat recovery steam generator from service, which was expected to clear the way for General Electric to start installing equipment.

JPS said the project would add significantly to the country’s energy diversity, fuel security, flexible generation and production of clean energy.

New Fortress Energy began developing its terminal and pipeline at the Montego Freeport at the end of last year, but JPS has no stake in that project.