The oil-fired JPS power plant in Old Harbour Bay, St Catherine is to be replaced with a gas-fired plant.

The announcement of an agreement between Jamaica Public Service Company (JPS) and a Chinese firm is expected this week for the construction of the new energy plant at Old Harbour.

JPS and American company New Fortress Energy are executing separate projects at Old Harbour – the Jamaican utility company is building a new 190 MW plant, while Fortress is financing and developing the gas infrastructure to supply the plant with LNG.

Together, the projects are estimated at around US$500 million.

JPS said it will have no ownership in the gas infrastructure project nor contribute to the cost of developing it, but will solely be a client of New Fortress, which will build its pipeline to connect to the JPS plant. The same arrangement applies to the gas infrastructure under development by New Fortress in Montego Bay, which will feed gas to JPS’ Bogue plant.

The utility company said previously that the 190 MW combined cycle plant at Old Harbour is expect to cost close to US$300 million.

The name of the Chinese contractor will be disclosed only after the deal to develop the plant is finalised, JPS said. The utilitycompany had previously chosen Abengoa to develop the plant only to be embarrassed when the Spanish firm filed for bankruptcy protection in its home country just days later.

JPS is also in final negotiations with General Electric (GE) as the primary equipment supplier for the Old Harbour plant.

“JPS is currently finalising the agreements with both GE and the ‘EPC’ contractor and coordinating the start of this new generation facility with the completion of an associated LNG facility that will be built to provide gas. These two projects will total over US$500 million and begin operation in early 2018 with full commercial operation by the middle of 2018,” said JPS via email.

EPC is a categorisation, which stands for ‘engineering, procurement and construction’ contractor.

The plant’s advance GE turbines will utilise cleaner burning natural gas, replacing the heavy fuel oil currently used at Old Harbour, and will be able to integrate increased solar, wind and hydro resources as Jamaica moves towards producing more electricity from renewable resources.

“GE will provide four turbines – three gas turbines and one steam turbine the three heat recovery steam generators, the four electrical generators and the major controls,” said JPS.

Once the new Old Harbour plant is built, the current structure will be dismantled, and the property will resort to brownfield status, according to JPS spokeswoman Winsome Callum.

New Fortress is negotiating separately with the Electricity Sector Enterprise Team regarding its gas project, Callum said.

JPS has spent some US$4 million so far in preparing for the upgrade over the past 24 months.

The  Gleaner

The Jamaica Public Service has entered into a Memorandum of Understanding (MOU) with a China-based energy company to build the 190 MW Old Harbour Bay Power Station.

The Chinese company will replace the Spanish firm Abengoa, which filed for protection from creditors a few days after it was named as the preferred bidder for the construction of the power plant.

President and Chief Executive Office of JPS, Kelly Tomblin has said that the name of the company cannot be released due to confidentiality agreements, but that the company was well known in China and within the energy sector.

“JPS, given its continuing concerns for the financial viability and strength of Abengoa and their inability to meet our financial requirements, has moved to enter into an MOU agreement with a Chinese EPC provider,” she told The Gleaner.

Meeting With ESET

She pointed out that the name of the firm and the terms of the deal will be made public once discussions are complete.

Tomblin also indicated that JPS will be meeting with the Energy Sector Enterprise Team (ESET) next week Monday to discuss the new bidder and the finer details of a possible deal between both parties.

“We plan to meet with ESET on Monday afternoon to go through final details, and we will disclose more after that meeting.”

The JPS moved to assure stakeholders that the 190 MW project remains on track for the plant’s commissioning in 2018.

JPS says it was undaunted by the financial woes being faced by Abengoa and would be looking at alternatives.

“Abengoa was selected based on its wide-ranging and impressive technical expertise. The firm has constructed several combined cycle power plants around the world, and is also well known for its construction of renewable energy power plants. JPS also had the understanding that Abengoa’s financiers were committed to the company for the long term,” the company said in a press release.

The Gleaner

The Jamaica Public Service Company Ltd (JPS) has made good on its pledge to activate alternative plans to ensure the execution of the proposed 190-megawatt power plant at Old Harbour in St Catherine.

Yesterday, the light and power company said it was now in the final stages of negotiations with an alternate bidder to provide engineering, procurement and construction services, for the plant to be built in Old Harbour, St Catherine.

The original preferred bidder, Abengoa, was selected through a competitive tender process, with the assistance of two international consulting firms, AMEC Foster Wheeler and Power Engineers Collaborative LLC.

In November, the Spanish firm filed for protection from creditors – a possible first step towards filing for bankruptcy.

With the announcement of Abengoa’s financial challenges, JPS has been closely watching the progress of the Spanish company’s financial-restructuring plan.

However, Abengoa has not been able to provide the financial assurances required as a normal part of the process of confirming a bidder.

Kelly Tomblin, JPS president and chief executive officer, said: “We are very close to concluding key terms with one of our alternate bidders. Throughout this time, we have been working closely with the Electricity Sector Enterprise Team (ESET), so they are embedded in the process.”

Commenting on the importance of the project to Jamaica, Tomblin said: “We want to make it very clear that this project is not, and has never been, in danger. JPS shareholders (EWP and Marubeni) are the ones who have committed to bringing equity to the project, and there is keen interest and indicative commitment from a variety of financing sources. I want to make it very clear that the bidder on this project is not the financier. They are an engineering, procurement and construction firm, who will be subject to significant oversight and potential penalties for non-performance. We need to clear up any confusion on their role.”

The Gleaner

The oil-fired JPS power plant in Old Harbour Bay, St Catherine is to be converted to LNG.

Spanish firm Abengoa SA has revealed the value of the upgrade and employment prospects for the 190MW power plant project amid pre-bankruptcy filings in its home market.

“The contract for the plant, which will be powered by natural gas and cooled by seawater, is worth more than US$200 million,” said Abengoa in a release.

The engineering and renewable energy firm was selected as preferred bidder by Jamaica Public Service Company (JPS), and the parties are in the process of finalising the contract for the LNG-fired power plant. JPS has said the full project cost would be closer to US$300 million.

Abengoa has about four months in which to secure deals with its creditors and restructure its debts if it is to escape full bankruptcy. JPS has said it is not ready to give up on its preferred bidder just yet, but is monitoring the situation.

Abengoa said it will be responsible for the design, engineering and construction work of the plant that will replace an existing fuel-oil facility and is expected to “create between 300 and 500 jobs during the construction phase”.

JPS wants to decommission the existing fuel-oil plant and move to a natural gas facility to create a cleaner, efficient and more reliable source of power, added Abengoa.

The more than 40-year-old Old Harbour plant remains one of the least energy efficient in the island and its upgrade would form part of the Jamaican Government’s drive to increase cleaner forms of fuel. Jamaica aims to increase renewable energy reliance to 20 per cent of the energy output within the medium term.

SEAWATER COOLING SYSTEM

“The plant will use a seawater cooling system that returns the warm water without adversely impacting the environment. Abengoa’s design will use the existing infrastructure as much as possible, requiring less power and improving the overall output of the plant,” said the Spanish firm in late November, adding that the project would extend Abengoa’s experience in turnkey combined cycle projects to the Jamaican market.

The company informed that it filed for insolvency protection on November 25 before the Mercantile Courts of Seville. The company also indicated that it would continue negotiations with its creditors with the objective of reaching an agreement that ensures the company’s financial viability, “under the protection of Article 5 of the Spanish Insolvency Law”.

The company recorded a €194 million net loss attributable to its parent over nine months ending September 2015 on revenues of €4.87 billion. It holds €6.2 billion in total debt while its earnings before interest tax and amortisation totalled €1.3 billion or 4.5 times net leverage.

Abengoa’s other major combined-cycle projects include the 640MW plant in Centro Morelos, Mexico, and the 440MW combined cycle plant in Portland, Oregon, United States, currently under construction. More recently, Abengoa was awarded two combined cycle plants in Mexico – Nuevo Pemex 680MW, and Norte III, 924MW.

The Gleaner

LIGHT AND power providers, the Jamaica Public Service Company (JPS) said yesterday that it is getting independent advice from its lawyers on whether to proceed with a contract with Spanish firm Abengoa to construct its power plant at Old Harbour, St Catherine.

Kelly Tomblin, the chief executive officer of JPS said yesterday that its shareholders held a conference call with Abengoa to discuss the way forward.

Abengoa’s chief executive Santiago Seage resigned yesterday after it emerged the Spanish renewable energy giant was close to bankruptcy.

The JPS, with the assistance of AMEC Foster Wheeler, a consultancy firm, selected Abengoa whose package consists of general electric combined cycle frame 6B gas turbine. The light and power company was in the process of negotiating a performance contract when the matter of the bankruptcy came to light.

“We were never going to enter into a performance contract until we had some assurance about their financial abilities,” Tomblin said.

She said that December 9 was the deadline for Abengoa to satisfy JPS of its ability to undertake the project and hinted that the light and power company is getting ready to move beyond Abengoa.

“Their problem is that they have some debt coming due but they don’t have the cash to pay. They are going to try to utilise their assets and do other things but that takes too long so we won’t be able to wait out that,” Tomblin said.

The Electricity Sector Enterprise Committee, ESET, said that while it is watching the developments, it is not totally concerned at this point.

Profesor Alvin Wint, a member of the ESET, said that in addition to Abengoa, other entities had submitted detailed bids to construct the power plant and they would be in line to be considered to take on the project.

“We will be requiring that they move quickly and if they need to go to a plan B they go quickly,” Wint said.

Both major shareholders of JPS, Marubeni and Korea East West Power Company Limited have committed to each inject up to 50 per cent of the approximately US$990 million equity that is required to develop the 190 megawatt power plant by year end.

The JPS intends to raise approximately US$210 million in debt funding to help finance the project.

The Gleaner

The JPS power plant in Old Harbour Bay, St Catherine. Ian Allen

Continuous tests as well as monitoring of the construction and commercial operation of the gas-fired 190-megawatt power plant to be developed by Jamaica Public Service Company (JPS) at Old Harbour Bay, St Catherine, have been promised, amid public concerns that the facility could eventually become a health hazzard.

Those health concerns were allayed by environmental consultant Carlton Campbell, who also assured the community in a consultation session Tuesday that they would have a mechanism for complaints for matters that arise when the project gets underway.

The public is weighing in on the environmental impact assessment report, which was done by Campbell’s company, CL Environmental Limited.

Such consultations are a precursor to final consideration and approval of a major project by the central authority, National Environment and Planning Agency (NEPA).

Site preparation for the liquefied natural gas plant is scheduled to begin by the first quarter of 2016 and construction by the second quarter. Commissioning of the plant is expected 22 months later, which would be close to mid-2018 if the current timetable holds.

JPS recently settled on Spanish engineering and renewable energy firm Abengoa to develop the plant, but that selection is now complicated by bankruptcy filings by the company on Wednesday, which is seeking protection in order to restructure its debt of about €9 billion. Spanish law gives it four months to strike deals with creditors under ‘pre-insolvency’ proceedings and avoid full bankruptcy.

The size of the contract to Abengoa was not disclosed, but previous reports say the project could cost around US$200 million to US$300 million. CL’s environmental impact report indicates that capital expenditure for construction of the plant is US$219.5 million, but last night JPS clarified that this figure related to equipment only. The utility said the full project cost would end up closer to US$300 million.

Deliver power supplies

The new plant will retire old capacity at Old Harbour, and is expected to deliver power supplies to the national electricity grid at less than 13 US cents per kilowatt-hour. The current plant is oil-fired.

Old Harbour residents were told to expect intermittent traffic disruptions and longer commutes, as well as increases in the cost of travel once the 190MW project enters the construction phase.

Campbell said the expected noise levels were compliant with the night and daytime standards of NEPA and the World Bank, and that water and air quality as well as drainage and wastewater systems would be monitored continuously.

“There is a perception that there will be health implications from this new plant,” said Campbell, while ticking off a list of reported concerns that included respiratory problems, increased noise levels, pollution, vibration and soot emissions.

However, he said, a health impact study was conducted which showed that residents would not be affected.

The environmental consultant also said the natural gas emissions and effluent released from the plant were not expected to harm the fish stock on which a lot of residents of the village depend for their livelihood.

The plant is expected to employ 400-450 during construction, and 45 persons permanently at commissioning.

The project was submitted to NEPA for approval on September 2, 2014, and after initial review, the agency requested that JPS produce an environmental impact report. The report was submitted at the end of October and is under review by various agencies.

Their feedback will eventually be communicated to JPS.

“The agencies will therefore refrain from making any comments or answering any questions in relation to the development at this time, as the application is currently the subject of review,” said NEPA official Ruth-Ann Lacey-Sherrard at Tuesday night’s public consultation.

The presence of the agencies at the event, she said, was merely to observe and take note of public comments that would inform the deliberations of the Natural Resources Conservation Authority (NRCA) which is a division of NEPA.

“Please note, carefully, that the final decision on the application is the sole responsibility of the NRCA,” Lacey-Sherrard said.

“The agencies’ review of the public presentation and consultation processes is extremely important in the decision-making process. These consultation processes provide an additional opportunity for stakeholders to air their concerns, make comments, provide opinions and views on the development project, and afford the applicant the opportunity to address these,” she said.

The Gleaner

JPS to open discussions with other renewable vendors

The Jamaica Public Service (JPS) yesterday announced that it will be engaging in discussions with other renewable vendors to ensure execution of the planned energy 190 MW Power Plant in Old Harbour, St. Catherine.

Chief Executive Officer, Kelly Tomblin in a press release advised the public that Spanish renewable energy and engineering firm Abengoa has filed for protection from creditors – an initial step towards filing for bankruptcy. The company was recently announced as the preferred bidder to construct the combined-cycle plant in Old Harbour.

“While JPS notes the development with regret, it is fully prepared to activate its alternative plans to ensure the execution of the project, which will replace the present Old Harbour Bay Power Station, while adding more Liquefied Natural Gas to the country’s energy mix,” Tomblin stated.

“We will be having dialogue with Abengoa — but JPS remains undaunted by the news. As a responsible corporate entity, our company has been in full preparation mode for any type of challenge regarding the completion of this project. We will not be derailed from our mission to bring real change to the energy sector and by extension, to Jamaica,” she continued.

The CEO reportedly stated that JPS has been eyeing other vendors since the announcement of the Abengoa’s financial situation.

Abengoa, which reported debt of ¤8.9-billion in its third quarter financials, began bankruptcy protection proceedings to avoid what could be one of Spain’s largest insolvencies.

The figure could be doubled when including ¤2.1 billion in funds it owed to suppliers and ¤5.9 billion of debt the company has in subsidiaries it said could potentially be sold. According to reports, the company has filed for protection from creditors with hopes of reaching a deal on its debts by March.

According to Tomblin, Abengoa was selected based on its wide ranging and impressive technical expertise. The company has been touted as one of the world’s top builders of power lines transporting energy across Latin America and a top engineering and construction business, making massive renewable-energy power plant.

The light and power company also had the understanding that Abengoa’s financiers were committed to the company for the long term.

“JPS wishes to assure its customers and all stakeholders that the 190 MW project remains on track for the plant’s commissioning in 2018.The Company will keep stakeholders informed as events unfold,” she said.

Jamaica Observer

 

Although Abengoa, the Spanish company selected as the preferred bidder to build a major power plant in Jamaica, has initiated steps that could lead to a bankruptcy declaration, Jamaica Public Service Company CEO Kelly Tomblin is not yet ready to call it quits on the multinational corporation.

Reacting to news of the bankruptcy proceedings initiated by Abengoa, Tomblin said she was monitoring the situation of the Spanish renewable-energy company.

It was only last week that JPS announced Abengoa as the preferred bidder to build the 190-megawatt combined-cycle plant in Old Harbour, St Catherine.

Despite fears that Abengoa may not be able to fulfil the requirements of the bid, given its precarious financial situation, Tomblin is holding out hope that the company will be able to make good on its financial obligations in relation to the bid.

“We have been monitoring the situation for some time. We have backup plans, but we have to wait and see what Abengoa shows us. But pot can’t call kettle black because JPS, as you know, has had its own financial difficulties, and we are just now emerging from those, so we know what it’s like, so we want to make sure that we don’t overreact,” Tomblin told The Gleaner last evening.

In the event that Abengoa folds completely, Kelly Tomblin pointed out that JPS has several alternatives.

“There are other vendors. We have many vendors who were poised to build the plant, so if, in fact, Abengoa can’t show, then other people can build the power plant. As you know, we have shareholders who have deep expertise, but we don’t want to jump the gun. Of course, Abengoa will have to give us financial assurance, but, again, pot can’t call the kettle black. It wasn’t very long ago that JPS, too, was facing insolvency problems,” she said.

Energy Minister Phillip Paulwell, in reacting to the news, said there was no need to panic and that JPS should be given the space to continue the procurement process.

When asked if the situation vindicates him in respect of the Energy World International (EWI) bid, Paulwell said, “There will be vindication when the gas is here because that, for me, is the most important aspect.”

Paulwell was in charge of overseeing the Government’s 391-megawatt project, which awarded a bid to EWI, a company which faced financial woes, leading to questions about its ability to deliver on the bid. This was before responsibility for the project was handed over to the Vin Lawrence-led enterprise team.

Now, with news of Abengoa’s bankruptcy filing, Jamaica’s renewable-energy plans may be delayed yet again.

Abengoa’s latest financial woes sent shockwaves through the banking sector and financial markets in Spain yesterday, fuelling concerns that the country’s lenders may be left with heavy losses.

According to international media reports, Abengoa has been having financial challenges from as far back as 2013, when Spain instituted energy reforms, which reduced subsidies to renewable-energy providers. This affected Abengoa’s capital base significantly and further exacerbated its pile-up of debt.

The Financial Times has said that a possible default by Abengoa could count as the largest bankruptcy in Spanish history, given that as of September, Abengoa carried gross debt of £8.9 billion.

The filing for preliminary creditor protection yesterday came after a potential investor cancelled plans to inject £350 million into the company.

While he could not comment on questions of whether due diligence was done on the Abengoa bid, Private Sector Organisation of Jamaica CEO Dennis Chung said news of the filing does not mean the company will go under, as bankruptcy proceedings often give a company an opportunity to rebuild.

“I couldn’t comment on due diligence. I have to believe that proper due diligence would have been done, so that question should be put to the person who actually did the due diligence,” Chung said.

 

The Gleaner

* Abengoa has 4 months to reach deal with creditors

* Shares plummet 54 pct, bonds virtually worthless

* Abengoa’s bankruptcy would be Spain’s largest on record (Adds Abengoa removed from Ibex, details on company)

MADRID, Nov 25 Spain’s Abengoa started insolvency proceedings on Wednesday after a potential investor said it would not inject fresh capital into the energy firm, sending its share price tumbling by 54 percent.

Under Spanish law, companies can enter into pre-insolvency proceedings, giving them up to four months to reach an agreement with creditors to avoid a full-blown insolvency process and a potential bankruptcy.

Failure by Abengoa to reach such a deal could lead to Spain’s largest bankruptcy on record. The company employs around 24,000 people worldwide.

Spanish and international banks’ total exposure to Abengoa stands at around 20.2 billion euros ($21.4 billion), including financing for projects, a source familiar with the matter said at the end of September.

The Seville-based engineering and renewable energy firm, which has biofuel and solar-heated power plants in the United States, has been struggling for a year with high debts but the situation became unsustainable in July. It first cut its 2015 targets and stepped up an asset sales plan on July 31, only to announce a share issue days later.

Since then, the company’s market value has tumbled by around 85 percent, hit by uncertainties over whether creditor banks would agree to back the issue.

The shares plummeted by 69 percent when trading resumed following a more than three-hour suspension on Wednesday morning. They closed down 54 percent, wiping out around 470 million euros in market value on the day.

The stock market operator said Abengoa would be removed from Spain’s blue-chip index Ibex as of Nov. 27.

Bonds also lost most of their value.

Abengoa earlier confirmed that Gonvarri, a unit of privately-held industrial group Gestamp, had backed away from a plan to inject around 350 million euros into the firm.

“The company will begin the negotiating process with its creditors with the aim to reach an accord to guarantee the financial viability under the Article 5 of the Bankruptcy act, which the company intends to request as soon as possible,” Abengoa said in a statement.

Abengoa has been trying to find new investors since early August, when it announced a 650 million euro rights issue of new shares to cut gross debt of some 8.9 billion euros.

Gonvarri’s interest was conditional on banks underwriting the issue and it had asked the banks to inject 1.5 billion euros in to the company, sources told Reuters late on Tuesday.

Earlier this month, Abengoa’s auditor Deloitte said the group faced significant risks and its future depended heavily on the proposed investment deal with Gonvarri.

https://solarbuzzjamaica.com/jps-announces-preferred-bidder-for-old-harbour-plant/

Reuters.com

 

The Jamaica Public Service Company Limited (JPS) has announced the selection of Spanish firm Abengoa as the preferred bidder to build the 190 megawatt Combined Cycle plant in Old Harbor, St Catherine. 

The announcement follows the approval by the Electricity Sector Enterprise Team for the company to start negotiations with US-based New Fortress Energy for the supply of natural gas to the plant.

The JPS says once contracted, Abengoa will be responsible for the design, engineering and construction work on the plant.

It will be built close to company’s existing power station in Old Harbour Bay.

The JPS says it is in the process of procuring the necessary permits for the construction of the plant.

It says as part of its public education, it has shared the Environmental Impact Assessment on its website and will host a public consultation meeting next Tuesday in Old Harbour Bay.

The JPS says the gas terminal and the new gas-fired power plant will allow it to retire 220 megawatts of existing oil-fired steam generation units at Old Harbour and Hunts Bay in 2018.

It says this will ultimately result in a reduction of over 1.2 million barrels of oil per year and allow for power generation below 13 United States cents per kilowatt hours.

The Gleaner