New Fortress Energy was issued at the weekend with a stop order by the National Environment and Planning Agency (NEPA) on pipe-laying works to link its LNG terminal to the Jamaica Public Service Company’s (JPS) Bogue plant in Montego Bay.

Representatives of the company, following a meeting with NEPA Tuesday morning, managed to secure a new permit allowing work to continue on the project, which has an end-of-summer deadline to start supplying gas to JPS.

New Fortress, a subsidiary of Fortress Investment Group LLC, is currently laying the pipelines from the port to the 120MW Bogue plant, but has faced setbacks getting landowners to allow the pipes to pass through their property.

“It’s a minor issue, actually. We had some property owners that were being difficult about their rights of way. So Fortress had taken a different route, which wasn’t permitted. They had to go back to get the permit just for the switch in the route,” JPS boss Kelly Tomblin told Gleaner Business.

She said, initially, all landowners were in agreement with the route “but then a property owner changed their mind”.

New Fortress had gone to NEPA for approval of the new route, but “NEPA hadn’t approved it yet. They did so today (Tuesday),” Tomblin said, while conceding that work on the project had continued.

Officials from NEPA visited the site at the weekend to enforce a stop order.

Tomblin said the project or its timelines won’t suffer any adverse fallout from the work stoppage, which roughly spanned two working days.

“I’m sure they can make that up,” she said.

New Fortress said as much last night, after affirming “utmost respect” for planning rules.

“We have received official notice that work can continue on our pipeline installation, subject to our permit conditions,” said New Fortress spokesman Jake Suski.

“We have the utmost respect for the rules and process and will continue to take direction from NEPA around permit issues. At this time, we don’t anticipate any delays as a result of these conversations around the pipeline installation,” he said.

The LNG project is already running about five months behind its original schedule. Gas delivery should have begun in April.

“The point is, we want to get gas to this power plant very quickly. So Fortress was moving very quickly. But we have to make sure we work very closely with the regulator and I think Fortress understands that now,” said Tomblin.

tameka.gordon@gleanerjm.com

 

The Gleaner

The JPS power plant in Old Harbour

 

In an update last week on the US Department of Energy’s (DOE) website American LNG— associate company of New Fortress Energy – said there were likely to be delays at its planned US$250-million onshore LNG export facility at Titusville, Florida. Operations will likely begin in 2017, not in April 2016 as projected before.

American LNG is controlled by Fortress Equity Partners, which is also the parent of New Fortress Energy.

New Fortress Energy won out of a field of eight bidders to provide a long-term natural gas solution for JPS power plants, starting with Bogue in Montego Bay.

In March this year, New Fortress also secured the contract to supply gas to the planned Jamaica Public Service Company (JPSco) Ltd 190MW power plant in Old Harbour, St Catherine.

American LNG, on March 7 committed to supply New Energy with up to 2.26 Bcf/year (billion cubic feet per year).

Overall, American LNG received approval in 2015 to export up to 600,000 mt/year of LNG (approximately 30.2 Bcf/year regasified) in ISO containers to countries with which the US has free-trade agreements.

Now it said that developments at its Titusville facility indicated a likely commercial operation date in 2017 instead of April 2016.

Efforts by the Jamaica Observer to find out from New Fortress how this would affect plans for Bogue were not answered up to press time.

New Fortress last year signed the supply accord with JPSCo to provide LNG for the power company’s 120-MW Bogue power plant at Montego Bay. To this has been added Old Harbour.

The 190MW gas-fired plant is intended to replace 292 megawatts of Heavy Fuel Oil Power Plants in Old Harbour and Hunts Bay which are being phased out.

American LNG told the Department of Energy that it is now producing LNG from its Hialeah facility near Miami from which the first export of LNG occurred February 5.

Natural gas for the facility is supplied by Peninsula Energy Services Co to an affiliate of American LNG.

The project has approval to export LNG in ISO containers to non-free trade agreement nations.

In March, LNG World news online reported that American LNG made the first export from the facility on February 5, 2016.

 